University Information Technology Services (UITS) Shrewsbury Data Center Scheduled Maintenance
Scheduled Maintenance Report for UMass Shared Services
Completed
The scheduled maintenance has been completed.
Posted Feb 25, 2017 - 22:07 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 25, 2017 - 17:00 EST
Scheduled
WHAT: The UITS Infrastructure Team will be conducting scheduled maintenance in the UITS South Street Shrewsbury Data Center.

IMPACT: From 5pm to 11pm there may be interruptions accessing the UMass Shared Services (e.g.HR Direct, Finance, Student applications, etc.*). Please plan accordingly.

*This scheduled maintenance affects the following UITS Supported applications: IDM, Summit (Summit - Finance, Summit - HR, Summit - Student), Finance Systems (Finance Production, Finance Reporting, BuyWays, Effort Certification), Student Services (Student Production (Boston, Dartmouth, Lowell), Admissions - UMass Custom Application, Admissions - Check Status, Housing RMS Dartmouth, Housing StarRez Lowell, u.achieve Boston, eTranscript, Parent Access), Legal Systems (Case Logistix, Legal Files), EAB Lowell, R25 (R25 Boston, R25 Lowell), International Services (Terra Dotta - Travel Registry, Terra Dotta - Study Abroad, Sunapsis), HR Direct, Document Imaging (Boston, Dartmouth, Lowell), Cognos, DocStore, Citrix.

QUESTIONS: Please contact your respective application manager if you have any questions.
Posted Feb 24, 2017 - 16:26 EST