University Information Technology Services (UITS) Shrewsbury Data Center Scheduled Maintenance
Scheduled Maintenance Report for UMass Shared Services
Completed
The scheduled maintenance has been completed.
Posted 4 months ago. Mar 18, 2018 - 00:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 4 months ago. Mar 17, 2018 - 17:00 EDT
Scheduled
WHAT: The UITS Infrastructure Team will be conducting scheduled maintenance in the UITS Shrewsbury Data Center.

IMPACT: From 5:00 PM on Saturday, March 17, 2018 until 12 Midnight access to all UMass Shared Services production environments will be unavailable due to UITS Shrewsbury Data Center maintenance. This includes many applications and systems including HR Direct, Finance, BuyWays, Student and applicant systems for Boston, Dartmouth, Lowell and Worcester, Summit, Document Imaging and International Systems.
Posted 4 months ago. Mar 12, 2018 - 16:38 EDT
This scheduled maintenance affected: Student Services (Student Production (Boston, Dartmouth, Lowell), Admissions - UMass Custom Application, Admissions - Check Status, Housing Dartmouth, Housing Lowell, u.achieve Boston, eTranscript, Parent Access, ID Email Lookup), Legal Systems (Case Logistix, Legal Files), International Services (Terra Dotta - Travel Registry, Terra Dotta - Study Abroad, Sunapsis), R25 (R25 Boston, R25 Lowell), Finance Systems (Finance Production, BuyWays, Effort Certification), Summit (Summit - Finance, Summit - HR, Summit - Student, Summit - Position Management), HR Direct, Document Imaging (Boston, Dartmouth, Lowell), and Web Services (Office 365).